NEW QUESTION 88
Who isresponsible for tracking the remaining work of the Sprint?

  • A. The Product Owner.
  • B. The Development Team.
  • C. The Development Team is consultation with the Product Owner.
  • D. The Project Manager.
  • E. The Scrum Master.

Answer: B

 

NEW QUESTION 89
In order to achieve the benefits of Scrum, it is important to enact the value of commitment. What two actions demonstrate the commitment of Scrum Team members? (Choose the best two answers.)

  • A. Do your best
  • B. Always deliver the items in the Sprint forecast.
  • C. Work late.
  • D. Send out a daily status report.
  • E. Help the other Scrum Team members.

Answer: A,E

 

NEW QUESTION 90
What two techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which development techniques to apply? (Choose the best two answers.)

  • A. Involve the complete Development Team.
  • B. Use coaching techniques; such as open questions and active listening.
  • C. Send every team member to the company's HR department to express their concerns.
  • D. Ask an external technical specialist to make the decision.

Answer: A,B

 

NEW QUESTION 91
What is the main reason for the Scrum Master to be at the Daily Scrum?

  • A. To make sure every team member answers the three questions.
  • B. To gather status and progress information to report to management.
  • C. To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.
  • D. He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.

Answer: D

 

NEW QUESTION 92
How much of the Sprint Backlog must be defined during the Sprint Planning event?

  • A. Enough so the Development Team can create its best forecast of what is can do, and to start the first
    several days of the Sprint.
  • B. The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.
  • C. Just enough to understand design and architectural implications.
  • D. Just enough tasks for the Scrum Master to be confident in the Development Team's understanding of
    the Sprint.

Answer: A

 

NEW QUESTION 93
The Product Backlog is ordered by:

  • A. Risk, where safer items are at the top, and riskier items are at the bottom.
  • B. The Product Owner with the most valuable items placed at the top.
  • C. Items are randomly arranged.
  • D. Size, where small items ale at the top and large items are at the bottom.

Answer: B

 

NEW QUESTION 94
Why should the Product Owner be present at the Daily Scrum? (Choose the best answer.)

  • A. To hear about impediments in functionality.
  • B. To represent the stakeholder's point of view.
  • C. To participate as a Scrum Team member.
  • D. He/She doesn't need to be there.

Answer: D

 

NEW QUESTION 95
Which topics should be discussed in the Sprint Review? (Choose the best answer.)

  • A. Coding and engineering practices.
  • B. All of the above.
  • C. The Scrum process, and how it was used during the Sprint.
  • D. The product Increment.

Answer: D

 

NEW QUESTION 96
Which statement best describes Scrum?

  • A. A cookbook that defines best practices for software development.
  • B. A defined and predictive process that confirms to the principles of Scientific Management.
  • C. A complete methodology that defines how to develop software.
  • D. A framework within which complex products in complex environments are developed.

Answer: D

 

NEW QUESTION 97
Every Development Team should have:

  • A. The competencies and skills needed to deliver a Done Increment in a Sprint.
  • B. At least one representative from each major software engineering discipline (like QA, Dev, UX).
  • C. One Lead Developer and no more than 8 other members.

Answer: A

 

NEW QUESTION 98
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

  • A. TheDevelopment Team.
  • B. The Product Owner.
  • C. The Scrum Team.
  • D. The Project Manager.

Answer: A

 

NEW QUESTION 99
What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement about which agile practices to apply? (Choose the best two answers.)

  • A. Involve the complete Scrum Team in making a decision.
  • B. Ask team members to take the issue up with to the company's Human Resources department.
  • C. Use coaching techniques; such as open Question:s and active listening.
  • D. Ask an external agile coach what they recommend.

Answer: A,C

 

NEW QUESTION 100
As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)

  • A. The Development Team works overtime during this Sprint.
  • B. Remove or change selected Product Backlog items.
  • C. Cancel the Sprint.
  • D. The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress.
  • E. Recruit additional Development Team members before the work can begin.

Answer: B,D

 

NEW QUESTION 101
Who has the final say on the order of the Product Backlog?

  • A. The Stakeholders.
  • B. The CEO.
  • C. The Product Owner.
  • D. The Scrum Master.
  • E. The Development Team.

Answer: C

 

NEW QUESTION 102
When does the next Sprint begin?

  • A. Immediately after the conclusion of the previous Sprint.
  • B. Immediately following the next Sprint Planning.
  • C. The Monday following the Sprint Review.
  • D. When the Product Owner is ready.

Answer: A

 

NEW QUESTION 103
Who is responsible for clearly expressing Product Backlog items?

  • A. The business analyst who represents the Product Owner in the Development Team.
  • B. The Scrum Master, or the Scrum Master may have the Development Team do it.
  • C. The Product Owner.
  • D. The Scrum Master.

Answer: C

 

NEW QUESTION 104
What does it mean to saythat an event has a time-box?

  • A. The event must happen at a set time.
  • B. The event must happen by a given time.
  • C. The event can take no more than a maximum amount of time.
  • D. The event must take at least a minimum amount of time.

Answer: C

 

NEW QUESTION 105
Which three of the following are time-boxed events in Scrum? (Choose three.)

  • A. Sprint Planning.
  • B. Release Testing.
  • C. Daily Scrum.
  • D. Sprint Retrospective.
  • E. Sprint 0.
  • F. Sprint Testing.
  • G. Release Retrospective.

Answer: A,C,D

 

NEW QUESTION 106
Which two of the following are true about the Scrum Master role? (Choose the best two answers.)

  • A. The Scrum Master assigns tasks to Development Team members when they need work.
  • B. The Scrum Master helps those outside the team interact with the Scrum Team.
  • C. The Scrum Master teaches the Development Team to keep the Scrum meetings to their time-box.
  • D. At the Sprint Review, the Scrum Master identifies what has been "done" and what has not been "done".
  • E. The Scrum Master is responsible for updating the Sprint Burndown.

Answer: A,C

 

NEW QUESTION 107
A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take? (Choose the best answer.)

  • A. Set up the meeting and tell the Development Team that is how it will be done.
  • B. Allow the Development Team to self-manage and determine for itself what to do.
  • C. Inform management and ask them to solve it.
  • D. Ask the Development Team members to alternate who is responsible for meeting setup.

Answer: B

 

NEW QUESTION 108
A new developer is having continuing conflicts with existing Development Team members and creating a hostile environment. If necessary, who is responsible for removing the team member?

  • A. The Development Team is responsible, and may need help from the Scrum Master.
  • B. The Scrum Manager is responsible, because he/she removes Impediments.
  • C. The Product Owner is responsible, because he/she controls the return on investment (ROI).
  • D. The hiring manager is responsible, because he/she hired the developer.

Answer: B

 

NEW QUESTION 109
What are two ways that architecture and infrastructure are handled in Scrum? (Choose two.)

  • A. They are implemented along with functional development of the product.
  • B. They are built by a separate team through the creation of an architectural runway.
  • C. They are discussed, determined, and documented before the actual feature development Sprints.
  • D. They are added to the Product Backlog and addressed in early Sprints, while always requiring at least some business functionality, no matter how small.

Answer: A,D

 

NEW QUESTION 110
......