NEW QUESTION 33
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.
- A. The planning strategy is infinite.
- B. The work center has several individual capacities.
- C. The Change Planning Direct on indicator is set.
- D. Alternative resources are fully occupied.
Answer: A,B
NEW QUESTION 34
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?
- A. Work center hierarchy
- B. Operation network
- C. Resource network
- D. Setup matrix
Answer: A
NEW QUESTION 35
What is the difference between co-products and by-products?
- A. Only co-products appear in the processor production order settlement rule.
- B. Only co-products are identified by a special item category in the bill of material (BOM).
- C. Only by-products have a zero inventory valuation.
- D. Onlyco-products can be manufactured in isolation from the main product.
Answer: A
NEW QUESTION 36
MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?
- A. It is converted into a production order.
- B. It is converted into a planned order.
- C. It is converted into a reservation.
- D. It is converted into a schedule line.
Answer: C
NEW QUESTION 37
Advanced Planning uses master data and transaction data from SAP S/4HANA In which data obje can you set the advanced planning flag? Note: There are 2 correct answers to this question.
- A. Material
- B. Plant
- C. Production version
- D. Work center
Answer: A,D
NEW QUESTION 38
What does it mean for the production planner when MRP works with infinite capacities?
- A. MRP creates capacity requirements only if the work center has sufficient capacity.
- B. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
- C. MRP creates capacity requirements without checking the capacity of a work center.
- D. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
Answer: C
NEW QUESTION 39
You want to insert an operation at a certain time on a work center. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?
- A. The previously dispatched operation stays as is the new operation is insertedafter the dispatched operation.
- B. The new operation is inserted at the desired time the previously dispatched operation is moved backward.
- C. The previously dispatched operation stays assist the new operation is inserted before the dispatched operation.
- D. The new operation is inserted at the desired time; the previously dispatched operation is moved forward.
Answer: B
NEW QUESTION 40
You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?
- A. Squeezing
- B. Find Slot
- C. Scheduling working time only
- D. Insert operation
Answer: B
NEW QUESTION 41
For a production version to be valid and consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.
- A. The assigned routing and bill of materials (BOM) must be valid in the entire validity period.
- B. The assigned routing must NOT have alternative sequences.
- C. Thedeletion flag must NOT be set for the bill of materials (BOM) or the routing.
- D. The lot size range must be within the lot-size range of the assigned routing.
- E. The assigned routing must be a rate routing.
Answer: A,C,D
NEW QUESTION 42
Where do you maintain the duration of a producton operation?
- A. Material master
- B. Routing
- C. Bill of material (BOM)
- D. Work instructions
Answer: B
NEW QUESTION 43
Which of the following is a valid sequence of the main activities in product on order processing?
- A. Creation, staging, release, material withdrawal, confirmation
- B. Creation, scheduling, release, variance calculation, confirmation
- C. Creation, scheduling, release, material withdrawal, confirmation
- D. Creation, release, scheduling, material withdrawal, confirmation
Answer: C
NEW QUESTION 44
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.
- A. Wait time
- B. Move time
- C. Float before production
- D. Pick/pack time
- E. Queue time
Answer: A,D,E
NEW QUESTION 45
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.
- A. Run PP/DS heuristics for repetitive manufacturing.
- B. Run MRP with automatic selection of production version.
- C. Assign planned orders manual lying the planning table.
- D. Run MRP with quotaarrangement.
Answer: A,D
NEW QUESTION 46
If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?
- A. Fill up based on the lot size procedure
- B. Fill up to the safety stock level
- C. Fill up to the reorder stock level
- D. Fill up to the maximum stock level
Answer: A
NEW QUESTION 47
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.
- A. To determine the work in progress along the production line
- B. To provide timely updates of inventory management for the staged components
- C. To stage different components for a production line simultaneously
- D. To reduce the totalproduction lead time for along production line
Answer: A,B
NEW QUESTION 48
You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.
- A. Individualconversion
- B. Partial conversion
- C. Order release
- D. Full conversion
Answer: B,D
NEW QUESTION 49
How would you define pegging in the context of Advanced Planning?
- A. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
- B. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.
- C. An evaluation that is ordered according to thebill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
- D. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.
Answer: C
NEW QUESTION 50
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stockis zero and the discontinuation date is in the past?
- A. Production order release
- B. Kanban
- C. Back flushing
- D. Material requirements planning
Answer: D
NEW QUESTION 51
What are the consequences if operation status Dispatched is set for a production order operation?
- A. You can reschedule the operation using lead the scheduling.
- B. You canreschedule the order using material requirements planning.
- C. You can reschedule the operation using finite Scheduling in a planning board.
- D. You can reschedule the order using lead time scheduling.
Answer: C
NEW QUESTION 52
What are the possible results of a production planning run inAdvanced Planning (PP/OS)? Note: There are 3 correct answers to this question.
- A. Scheduling agreement schedule line
- B. Purchase requisition
- C. Production order
- D. Stock transport order
- E. Planned order
Answer: A,B,E
NEW QUESTION 53
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.
- A. Order-related
- B. Milestone-related
- C. Cost-related
- D. Product-related
Answer: A,D
NEW QUESTION 54
The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?
- A. Use the minimum order quantity.
- B. Use the MRP type for vendor managed inventory.
- C. Use the fixed lot size procedure.
- D. Use the reorder point.
Answer: C
NEW QUESTION 55
......