NEW QUESTION 33
What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.

  • A. The planning strategy is infinite.
  • B. The work center has several individual capacities.
  • C. The Change Planning Direct on indicator is set.
  • D. Alternative resources are fully occupied.

Answer: A,B

 

NEW QUESTION 34
Your project uses process orders for the production of liquid chemicals. What can you define to ensure that the production flow happens only in physically connected tanks?

  • A. Work center hierarchy
  • B. Operation network
  • C. Resource network
  • D. Setup matrix

Answer: A

 

NEW QUESTION 35
What is the difference between co-products and by-products?

  • A. Only co-products appear in the processor production order settlement rule.
  • B. Only co-products are identified by a special item category in the bill of material (BOM).
  • C. Only by-products have a zero inventory valuation.
  • D. Onlyco-products can be manufactured in isolation from the main product.

Answer: A

 

NEW QUESTION 36
MRP created a planned order for a material that has one single material from stock as a component. What happens to this dependent requirement when you convert the planned order into a production order?

  • A. It is converted into a production order.
  • B. It is converted into a planned order.
  • C. It is converted into a reservation.
  • D. It is converted into a schedule line.

Answer: C

 

NEW QUESTION 37
Advanced Planning uses master data and transaction data from SAP S/4HANA In which data obje can you set the advanced planning flag? Note: There are 2 correct answers to this question.

  • A. Material
  • B. Plant
  • C. Production version
  • D. Work center

Answer: A,D

 

NEW QUESTION 38
What does it mean for the production planner when MRP works with infinite capacities?

  • A. MRP creates capacity requirements only if the work center has sufficient capacity.
  • B. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
  • C. MRP creates capacity requirements without checking the capacity of a work center.
  • D. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.

Answer: C

 

NEW QUESTION 39
You want to insert an operation at a certain time on a work center. The planning direction is forward. The desired dispatching time coincides with an operation that has previously been dispatched. How does the insertion take place?

  • A. The previously dispatched operation stays as is the new operation is insertedafter the dispatched operation.
  • B. The new operation is inserted at the desired time the previously dispatched operation is moved backward.
  • C. The previously dispatched operation stays assist the new operation is inserted before the dispatched operation.
  • D. The new operation is inserted at the desired time; the previously dispatched operation is moved forward.

Answer: B

 

NEW QUESTION 40
You want to schedule an operation finitely, without moving other operations. Which scheduling strategy do you select?

  • A. Squeezing
  • B. Find Slot
  • C. Scheduling working time only
  • D. Insert operation

Answer: B

 

NEW QUESTION 41
For a production version to be valid and consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.

  • A. The assigned routing and bill of materials (BOM) must be valid in the entire validity period.
  • B. The assigned routing must NOT have alternative sequences.
  • C. Thedeletion flag must NOT be set for the bill of materials (BOM) or the routing.
  • D. The lot size range must be within the lot-size range of the assigned routing.
  • E. The assigned routing must be a rate routing.

Answer: A,C,D

 

NEW QUESTION 42
Where do you maintain the duration of a producton operation?

  • A. Material master
  • B. Routing
  • C. Bill of material (BOM)
  • D. Work instructions

Answer: B

 

NEW QUESTION 43
Which of the following is a valid sequence of the main activities in product on order processing?

  • A. Creation, staging, release, material withdrawal, confirmation
  • B. Creation, scheduling, release, variance calculation, confirmation
  • C. Creation, scheduling, release, material withdrawal, confirmation
  • D. Creation, release, scheduling, material withdrawal, confirmation

Answer: C

 

NEW QUESTION 44
Which time elements are part of a routing operation? Note: There are 3 correct answers to this question.

  • A. Wait time
  • B. Move time
  • C. Float before production
  • D. Pick/pack time
  • E. Queue time

Answer: A,D,E

 

NEW QUESTION 45
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A. Run PP/DS heuristics for repetitive manufacturing.
  • B. Run MRP with automatic selection of production version.
  • C. Assign planned orders manual lying the planning table.
  • D. Run MRP with quotaarrangement.

Answer: A,D

 

NEW QUESTION 46
If the stock level drops below the reorder stock in reorder point planning, what is the system logic to trigger procurement?

  • A. Fill up based on the lot size procedure
  • B. Fill up to the safety stock level
  • C. Fill up to the reorder stock level
  • D. Fill up to the maximum stock level

Answer: A

 

NEW QUESTION 47
What is the purpose of a reporting point confirmation in repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A. To determine the work in progress along the production line
  • B. To provide timely updates of inventory management for the staged components
  • C. To stage different components for a production line simultaneously
  • D. To reduce the totalproduction lead time for along production line

Answer: A,B

 

NEW QUESTION 48
You want to create a production order from a planned order. What methods could you use? Note: There are 2 correct answers to this question.

  • A. Individualconversion
  • B. Partial conversion
  • C. Order release
  • D. Full conversion

Answer: B,D

 

NEW QUESTION 49
How would you define pegging in the context of Advanced Planning?

  • A. An evaluation to verify if there are overstock situations in the balance between receipt and issue elements after the production planning run.
  • B. An evaluation that is ordered according to the network structure of all related products and represents the coverage of issue elements with receipt elements.
  • C. An evaluation that is ordered according to thebill-of-material structure of all related products and represents the relationship between the receipt and the issue elements.
  • D. An evaluation to verify if there are mater al or capacity shortages in the network after the production planning run.

Answer: C

 

NEW QUESTION 50
You have maintained the parameters for simple discontinuation the material master of a component. Which business process will be affected if the available stockis zero and the discontinuation date is in the past?

  • A. Production order release
  • B. Kanban
  • C. Back flushing
  • D. Material requirements planning

Answer: D

 

NEW QUESTION 51
What are the consequences if operation status Dispatched is set for a production order operation?

  • A. You can reschedule the operation using lead the scheduling.
  • B. You canreschedule the order using material requirements planning.
  • C. You can reschedule the operation using finite Scheduling in a planning board.
  • D. You can reschedule the order using lead time scheduling.

Answer: C

 

NEW QUESTION 52
What are the possible results of a production planning run inAdvanced Planning (PP/OS)? Note: There are 3 correct answers to this question.

  • A. Scheduling agreement schedule line
  • B. Purchase requisition
  • C. Production order
  • D. Stock transport order
  • E. Planned order

Answer: A,B,E

 

NEW QUESTION 53
How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.

  • A. Order-related
  • B. Milestone-related
  • C. Cost-related
  • D. Product-related

Answer: A,D

 

NEW QUESTION 54
The MRP run detected a shortage of a material that you source from an external supplier in full pallets. How can you make sure you will only receive full pallets?

  • A. Use the minimum order quantity.
  • B. Use the MRP type for vendor managed inventory.
  • C. Use the fixed lot size procedure.
  • D. Use the reorder point.

Answer: C

 

NEW QUESTION 55
......