NEW QUESTION # 45
Which of the following design features helps ensure thermal safety in buildings during extreme heat events by allowing passive cooling?
- A. High-performance insulation
- B. Double-glazed windows
- C. Operable windows
Answer: C
Explanation:
Operable windows can provide passive cooling by allowing occupants or building controls to introduce outdoor air when exterior temperature, humidity, and air quality conditions are suitable. During a power failure or mechanical-cooling interruption, natural ventilation can remove accumulated internal heat and improve survivability, particularly when combined with cross-ventilation, night flushing, shading, and ceiling fans. Double-glazed windows and high-performance insulation reduce unwanted heat transfer and are important envelope measures, but they do not independently provide ventilation or directly remove indoor heat. In a prolonged extreme-heat event, a tightly sealed building can still overheat from solar gains, occupants, lighting, and equipment. Operable windows therefore provide the listed feature that actively enables passive cooling and supports resilience when mechanical systems are unavailable.
NEW QUESTION # 46
A project pursuing LEED BD+C certification is designed with an electric air-source heat pump as the primary heating system to meet EAp1: Operational Carbon Projection and Decarbonization Plan. However, the client is considering adding a small natural-gas boiler for backup heating during extreme weather.
To earn maximum points under EAp1 while maintaining heating-system reliability, what should the LEED AP recommend regarding supplemental heating?
- A. Install a natural-gas boiler with automated controls that limit operation to extreme conditions and include provisions for future conversion to an all-electric system
- B. Design an all-electric supplemental heating system using electric-resistance elements or auxiliary heat-pump capacity to eliminate on-site fossil-fuel combustion
- C. Implement a wood-pellet biomass boiler as secondary heating because it qualifies as carbon-neutral without penalizing on-site combustion
Answer: B
Explanation:
An all-electric supplemental heating system maintains reliability without introducing on-site fossil-fuel combustion. Auxiliary heat-pump capacity or appropriately designed electric-resistance backup can operate during low outdoor temperatures when the primary heat pump cannot meet the full load. A natural-gas boiler would produce direct operational emissions even when used infrequently and would weaken the project's electrification and decarbonization pathway. Biomass combustion also creates on-site emissions and should not automatically be treated as carbon-neutral because its climate impact depends on fuel sourcing, combustion efficiency, supply chains, and accounting boundaries. The team should first reduce peak heating demand through envelope performance and then size the all-electric system for design conditions. This approach aligns with LEED v5's explicit focus on operational emissions and near-zero-carbon buildings.
NEW QUESTION # 47
A project design team for an elementary school project is attempting to achieve Innovation Credit, Innovation, Option 1. Innovation. Which of the following strategies would qualify?
- A. Pilot Credit from LEED Pilot Credit Library
- B. Exemplary Performance in Energy and Atmosphere Credit, Optimize Energy Performance
- C. Implement a building as a learning lab curriculum that has been piloted in three other primary schools in the district
- D. Create educational kiosks and posters around the school with picture of building systems' sustainable features
Answer: D
Explanation:
This strategy would qualify as an innovation credit because it is not addressed in the LEED green building rating system, and it achieves significant, measurable environmental performance by educating the students and the community about the benefits of green building. The project team would need to identify the intent, requirements, submittals, and design approach of this strategy in the Basis of Design document1. This strategy is also listed as an example of innovation in the LEED Innovation Catalog2.
NEW QUESTION # 48
When calculating the reverberation time of a room, which of the following pieces of information is least relevant?
- A. Operating sound level of nearest HVAC equipment
- B. Height and width of room
- C. Noise reduction coefficient of the ceiling surface
- D. Sound absorption coefficient of the floor surface
Answer: A
Explanation:
Explanation
When calculating the reverberation time of a room, the operating sound level of the nearest HVAC equipment is the least relevant piece of information. The reverberation time is the time it takes for the sound to decay by
60 decibels after the source stops emitting sound. The reverberation time depends on the volume and the surface area of the room, as well as the sound absorption coefficients of the materials that cover the surfaces.
The height and width of the room are needed to calculate the volume and the surface area. The noise reduction coefficient of the ceiling surface and the sound absorption coefficient of the floor surface are needed to calculate the total sound absorption of the room. The operating sound level of the nearest HVAC equipment is not relevant for calculating the reverberation time, but it may affect the background noise level and the speech intelligibility in the room.
References:
*LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit:
Acoustic Performance, page 7101
*Sounds of Silence: Acoustic Performance in LEED v4.12
NEW QUESTION # 49
A LEED AP submitted a Preliminary Design and Construction review and has received a review comment and technical advice on Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. Which of the following actions should the LEED AP do if the project continues to pursue LEED certification?
- A. Revise the documentation and resubmit the form
- B. Ask the General Contractor to be more aggressive with recycling goals
- C. Abandon meeting this prerequisite
- D. Submit an appeal to Green Business Certification Inc.
Answer: A
Explanation:
Revise the documentation and resubmit the form
If a project receives a review comment and technical advice on a prerequisite, it means that the documentation submitted was incomplete, inaccurate, or unclear, and that the project team needs to address the issues raised by the reviewer and provide additional information or clarification. The project team should revise the documentation and resubmit the form as part of the final review to demonstrate compliance with the prerequisite requirements. Abandoning meeting this prerequisite is not an option, as prerequisites are mandatory for LEED certification. Submitting an appeal to Green Business Certification Inc. is only applicable if the project team disagrees with the reviewer's decision or interpretation, and has additional evidence or arguments to support their claim. Asking the General Contractor to be more aggressive with recycling goals is not relevant to this prerequisite, as it does not address the documentation issue.
: As per the LEED AP Building Design + Construction (LEED AP BD+C) V4 resources, the Materials and Resources Prerequisite for Construction and Demolition Waste Management Planning requires the project team to develop and implement a construction and demolition waste management plan that identifies at least five materials targeted for diversion from disposal in landfills and incinerators. The project team must also estimate a diversion rate for each material and describe how they will achieve it. The project team must submit this plan as part of the preliminary design review, along with a letter from the owner or project manager confirming that they will implement it during construction. If the reviewer finds any issues with the plan or the letter, they will provide a review comment and technical advice on how to improve it. The project team must then revise the documentation and resubmit it as part of the final design review, along with a narrative describing how they addressed the reviewer's feedback. For more detailed information, you can refer to the web-based reference guide in the credit library atUSGBC's official website.
NEW QUESTION # 50
For an emergency care facility project, which of the following credits can be achieved if the total cost of permanently installed products are 25% cradle-to-cradle V3 Gold and 25% GreenScreen List Translator?
- A. Materials and Resources Credit, Building Life-Cycle Impact Reduction, Option 3. Building and Material Reuse
& Innovation Credit, Innovation, Exemplary Performance - B. Materials and Resources Credit, Furniture and Medical Furnishing, Option 3. Multi-Attribute Assessment of Products & Innovation Credit, Innovation, Exemplary Performance
- C. Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2.
Material Ingredient Optimization & Innovation Credit, Innovation, Exemplary Performance - D. Materials and Resources Credit, Furniture and Medical Furnishings, Option 3. Multi-Attribute Assessment of Products & Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2. Material Ingredient Optimization
Answer: C
Explanation:
The Materials and Resources Credit, Building Product Disclosure and Optimization, Material Ingredients, Option 2. Material Ingredient Optimization & Innovation Credit, Innovation, Exemplary Performance can be achieved if the total cost of permanently installed products are 25% cradle-to-cradle V3 Gold and 25% GreenScreen List Translator. This is because these certifications indicate that the materials used in the project have been assessed for their environmental and health impacts, contributing to the achievement of these credits.References: LEED AP Building Design + Construction (LEED AP BD+C) V4 resources 1
NEW QUESTION # 51
What is the maximum number of points a project pursuing LEED for New Construction can achieve under Location and Transportation Credit, Access to Quality Transit?
- A. Five points
- B. Four points
- C. Two points
- D. Three points
Answer: B
Explanation:
Explanation
According to the LEED v4: Building Design + Construction Guide, the Location and Transportation Credit, Access to Quality Transit has two options: Option 1. Transit-Served Location and Option 2. Transit Service Quality. Option 1 can earn 1 to 4 points depending on the percentage of functional entries within walking distance of transit stops or stations. Option 2 can earn 1 point if the project meets the minimum weekday and weekend headways for bus, streetcar, or informal transit stops, or rail stations or ferry terminals.The maximum number of points a project can achieve under this credit is 4 points by meeting both options1.References:
LEED v4: Building Design + Construction Guide, Location and Transportation Credit, Access to Quality Transit, Requirements1
NEW QUESTION # 52
A school wants to incorporate natural daylighting in classrooms on all sides of the building. What can the project design team explain to the school district about how this strategy will affect the operational energy cost?
- A. Having the lights off reduces the electricity use
- B. There would be passive solar heating benefits to all of the classrooms
- C. Heat gain will reduce the air conditioning load
- D. Reduction in lighting fixture use reduces re-lamping
Answer: A
Explanation:
Explanation
Natural daylighting can reduce the electricity use for artificial lighting, which is one of the major components of operational energy cost for buildings. By having the lights off or dimmed when sufficient daylight is available, the project can save energy and money. The other options are not necessarily true or relevant for natural daylighting. Heat gain and passive solar heating depend on the orientation, shading, and insulation of the windows, not just the amount of daylight. Reduction in lighting fixture use may reduce re-lamping, but that is not a significant factor in operational energy cost compared to electricity use. References: EA Credit Optimize Energy Performance, EQ Credit Daylight, LEED v4 Reference Guide for Building Design and Construction123
NEW QUESTION # 53
What is a viable strategy for optimizing open space under Sustainable Sites Credit, Open Space? U
- A. Minimize the floor-area ratio (FAR) and accessibility for open space
- B. Coordinate open space features early during the site planning phase
- C. Design a parking and road footprint layout that is not near open land
- D. Coordinate open space features during the construction phase
Answer: B
Explanation:
Coordinating open space features early during the site planning phase is a viable strategy for optimizing open space under Sustainable Sites Credit, Open Space. This can help to preserve natural habitats, reduce heat island effects, and enhance human health and well-being. The credit requires that the project provide outdoor space that is at least 30% of the total site area, and that at least 25% of that outdoor space meets certain criteria for vegetated, pervious, or shaded areas. Reference:
LEED credit library: This is the USGBC's comprehensive listing of all the LEED credits available in pursuing certification for your project. The credit library contains the requirements and guidance for each credit, as well as the web-based reference guide for the Building Design and Construction rating system.
Open Space: This is the specific credit page for the Open Space credit under the Sustainable Sites category. It provides the intent, requirements, and strategies for achieving the credit, as well as the number of points available and the applicable project types.
Step by Step Approach to Comply with the Open Space Credit in LEED v4: This is a blog post that explains the steps and calculations involved in complying with the Open Space credit. It also provides some examples and tips for optimizing open space design.
NEW QUESTION # 54
Which of the following projects is eligible to pursue the Energy and Atmosphere Prerequisite,Minimum Energy Performance, Option 2. Prescriptive Compliance: ASHRAE 50% Advanced Energy Design Guide?
- A. 50,000 ft2 (4 645 m2) office project
- B. 80,000 ft2 (7 432 m2) hospital project
- C. 140,000 ft2 (13 006 m2) retail project
- D. 110,000 ft2 (10 219 m2) school project
Answer: D
Explanation:
Explanation
The Energy and Atmosphere Prerequisite, Minimum Energy Performance, Option 2. Prescriptive Compliance:
ASHRAE 50% Advanced Energy Design Guide allows projects to follow the recommendations of the ASHRAE 50% Advanced Energy Design Guides (AEDGs) for different building types and climate zones. The AEDGs provide design guidance for buildings that use 50% less energy than those built to the requirements of the ANSI/ASHRAE/IES Standard 90.1-2004 commercial code1. However, not all building types and sizes are covered by the AEDGs. According to the LEED Reference Guide for Building Design and Construction2, the following building types and sizes are eligible for this option:
* Small to Medium Office buildings up to 100,000 ft2 (9 290 m2)
* Medium to Large Retail buildings up to 100,000 ft2 (9 290 m2)
* K-12 School buildings up to 200,000 ft2 (18 580 m2)
* Warehouse and Distribution Center buildings up to 500,000 ft2 (46 450 m2) Therefore, among the given options, only the school project is eligible to pursue this option, as it falls within the size limit for the K-12 School AEDG3.
References:
* LEED Reference Guide for Building Design and Construction v4
* Minimum Energy Performance - ASHRAE 90.1 - 2010
* ASHRAE 50% Advanced Energy Design Guide for K-12 School Buildings
* Advanced Energy Design Guides | Department of Energy
NEW QUESTION # 55
The WaterSense label or local equivalent requirement in Water Efficiency Prerequisite, Indoor Water Use Reduction ensures that eligible newly installed plumbing fixtures will
- A. comply with all international plumbing system requirements
- B. be advertised as LEED compliant
- C. comply with mandatory federal government regulations
- D. be both water efficient and high performing
Answer: D
Explanation:
The WaterSense label or local equivalent requirement in Water Efficiency Prerequisite, Indoor Water Use Reduction ensures that eligible newly installed plumbing fixtures will be both water efficient and high performing. The WaterSense label is a voluntary program by the U.S. Environmental Protection Agency (EPA) that identifies and promotes water-efficient products that meet EPA's specifications for water efficiency and performance. The label applies to tank-type toilets, water-using urinals, private lavatory faucets, and showerheads. For projects outside the U.S., local equivalents may be used if they meet the same criteria as WaterSense or are listed on the USGBC website. The label does not imply that the fixtures are LEED compliant, comply with mandatory federal government regulations, or comply with all international plumbing system requirements. Reference:
Water Efficiency Prerequisite: Indoor Water Use Reduction in LEED BD+C: New Construction v4.1 - LEED v4.11 What is the WaterSense Label and How Does it Apply?2 LEED QUALIFICATION GUIDE - v43 WaterSense Labeled Homes4
NEW QUESTION # 56
Which would contribute to compliance with Sustainable Sites Credit, Open Space?
- A. A forested area containing nature trails, that also achieves Sustainable Sites Credit, Site Development - Protect or Restore Habitat
- B. An intensive vegetated roof, provided the building has at least a 1.0 Floor to Area Ratio (FAR)
- C. A parking lot that serves as the location for a monthly flea market
- D. A mall with an indoor atrium, featuring a reflective roof
Answer: A
Explanation:
According to the LEED v4: Building Design + Construction Guide, the Sustainable Sites Credit, Open Space requires the project to provide outdoor space greater than or equal to 30% of the total site area (including building footprint). At least 25% of that outdoor space must be vegetated, have overhead vegetated canopy, or be a water body. Option A does not qualify as outdoor space, Option B is not vegetated or a water body, and Option C only applies to projects with a FAR of less than 1.0. Option D meets the requirements for both outdoor space and vegetation, and also contributes to the protection or restoration of habitat1. Reference: LEED v4: Building Design + Construction Guide, Sustainable Sites Credit, Open Space, Requirements1
NEW QUESTION # 57
What are the Storage and Collection of Recyclables requirements for only Retail projects under the Materials and Resources Prerequisite?
- A. Retail projects must conduct a waste stream audit for the duration of the project in an existing location or make projections based on historical data for similar establishments. Identify the top-five recyclable waste streams while stating the top-four waste streams where both collection and storage space will be provided
- B. Retail projects must conduct a waste stream audit once a month for the project in an existing or rented location or make projections based on data gathered from a previous cycle. Identify the top-three recyclable waste streams while stating the top-two waste streams where both collection and storage space will be provided
- C. Retail projects must conduct a waste stream audit for the once a year for the project in an existing or rented location or make projections based on the previous year's data for their business. Identify the top-four recyclable waste streams while stating the top-three waste streams where both collection and storage space will be provided
- D. Retail projects must conduct a waste stream audit twice a year for the project in an existing or rented location or make projections based on the previous year's data for their business. Identify the top-four recyclable waste streams while stating the top-three waste streams where both collection and storage space will be provided
Answer: A
Explanation:
Retail projects must conduct a waste stream audit for the duration of the project in an existing location or make projections based on historical data for similar establishments. Identify the top-five recyclable waste streams while stating the top-four waste streams where both collection and storage space will be provided. This is the requirement for Retail projects under the Materials and Resources Prerequisite, Storage and Collection of Recyclables, according to the LEED v4 BD+C Reference Guide1. The purpose of this prerequisite is to facilitate the reduction of waste generated by building occupants that is hauled to and disposed of in landfills1. The prerequisite applies to all LEED BD+C projects, but Retail projects have a different approach than other project types because of their unique waste streams and operational characteristics1. Retail projects must conduct a waste stream audit for the duration of the project in an existing location or make projections based on historical data for similar establishments. The audit or projection must identify the top-five recyclable waste streams by weight or volume using consistent metrics throughout1. The waste stream study period must be a minimum of 24 hours1. Retail projects must also provide dedicated areas that serve the entire building and are accessible to waste haulers and building occupants for the collection and storage of materials for recycling for at least four of the top-five recyclable waste streams identified by the audit or projection1. Reference:
Prerequisite: Storage and collection of recyclables | U.S. Green Building Council
NEW QUESTION # 58
Which strategy can maximize the efficiency of water use in an irrigation system?
- A. Set the irrigation controllers on a timer
- B. Space irrigation sprinkler heads for overlapping coverage
- C. Determine a set rate of irrigation and avoid adjustments
- D. Incorporate precipitation sensors with smart irrigation controllers
Answer: D
Explanation:
Incorporating precipitation sensors with smart irrigation controllers (C) maximizes irrigation efficiency by adjusting water usage according to real-time weather data and soil moisture levels, reducing unnecessary irrigation during rainfall. This LEED strategy helps conserve water and supports the Water Efficiency (WE) Credit: Outdoor Water Use Reduction. Fixed rates (A), timers (B), and overlapping sprinkler heads (D) do not optimize water based on environmental conditions, leading to possible water waste.
NEW QUESTION # 59
The design team and project owner decided not to pursue Energy and Atmosphere Credit, Enhanced Commissioning, but would hire a Commissioning Authority (CxA) to oversee the requirements for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification. What is a required responsibility for the CxA to achieve the stated objective?
- A. Develop a systems manual for the commissioned systems
- B. Review the building 10 months after substantial completion
- C. Verify that training requirements are completed
- D. Verify installation and performance of the commissioned systems
Answer: D
Explanation:
For LEED BD+C Energy and Atmosphere (EA) Prerequisite: Fundamental Commissioning and Verification, the CxA is responsible for verifying that building systems are properly installed and functioning correctly.
* This ensures compliance with the Owner's Project Requirements (OPR) and basis of design (BOD)
.
* Developing a systems manual (Option D) is required for Enhanced Commissioning, not Fundamental Commissioning.
* Reviewing the building after 10 months (Option B) is also part of Enhanced Commissioning, not Fundamental Commissioning.
* Training verification (Option C) is beneficial but not a core responsibility for Fundamental Commissioning.
Verifying installation and performance (Option A) is the primary requirement for the CxA under Fundamental Commissioning.
(Source: Official LEED BD+C Reference Manual)
NEW QUESTION # 60
A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions need to take place in order to meet compliance for Energy and Atmosphere Prerequisite, Fundamental Commissioning (Cx) and Verification?
- A. The PV system installer should commission his own installations and share the results with the project owner
- B. The Cx agent for the project must conduct or oversee the Cx of the PV system
- C. No action is necessary as the PV system is not required to be commissioned
- D. The building's mechanical engineer should commission his own installations and share the results with the project owner
Answer: B
Explanation:
The correct answer is C, the Cx agent for the project must conduct or oversee the Cx of the PV system. According to the LEED v4 Reference Guide for Building Design and Construction, the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification, requires that all energy-related systems, including renewable energy systems such as PV, be commissioned by an independent commissioning agent (CxA) or a qualified member of the project team who reports to the owner. The CxA or the qualified team member must perform or oversee all commissioning activities, including developing a commissioning plan, reviewing design documents and submittals, verifying installation and performance, and preparing a commissioning report12 Reference: 1: LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Prerequisite: Fundamental Commissioning and Verification, page 562. 2: LEED v4 Reference Guide for Building Design and Construction, Glossary, page 1020.
NEW QUESTION # 61
What Color Rendering Index (CRI) value meets the requirements of Indoor Environmental Quality Credit, Interior Lighting?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: D
Explanation:
Detailed Explanation:
A CRI value of at least 85 is required to meet the Indoor Environmental Quality Credit for Interior Lighting.
This ensures high-quality lighting that renders colors accurately, enhancing occupant comfort and visual experience. LEED emphasizes lighting design that supports functionality and wellbeing.
NEW QUESTION # 62
What is the maximum number of points a project pursuing LEED for New Construction can achieve under Location and Transportation Credit, Access to Quality Transit?
- A. Five points
- B. Four points
- C. Two points
- D. Three points
Answer: B
Explanation:
According to the LEED v4: Building Design + Construction Guide, the Location and Transportation Credit, Access to Quality Transit has two options: Option 1. Transit-Served Location and Option 2. Transit Service Quality. Option 1 can earn 1 to 4 points depending on the percentage of functional entries within walking distance of transit stops or stations. Option 2 can earn 1 point if the project meets the minimum weekday and weekend headways for bus, streetcar, or informal transit stops, or rail stations or ferry terminals. The maximum number of points a project can achieve under this credit is 4 points by meeting both options1. Reference: LEED v4: Building Design + Construction Guide, Location and Transportation Credit, Access to Quality Transit, Requirements1
NEW QUESTION # 63
A downtown office building is unable to construct dedicated parking for its occupants. However, the building developer has partnered with a parking garage to offer discounted parking for its occupants. If the discounted parking rate is $450 per month, how much must the rate be for green vehicles for the building to receive one point for Location and Transportation Credit, Green Vehicles?
- A. $360
- B. $405
- C. $90
- D. $225
Answer: C
Explanation:
For the building to receive one point for Location and Transportation Credit, Green Vehicles, the rate for green vehicles must be 80% less than the regular parking rate.Therefore, if the discounted parking rate is $450 per month, the rate for green vehicles must be $90 per month (20% of $450).
: LEED AP Building Design + Construction (LEED AP BD+C) V4 resources1
NEW QUESTION # 64
Which of these is a method to assess the regional context of a building's design for sustainability?
- A. Conducting a site analysis
- B. Improving a design threshold
- C. Consulting with neighbors
- D. Performing an energy analysis of the building
Answer: A
Explanation:
Conducting a site analysis is a method to assess the regional context of a building's design for sustainability.
A site analysis involves collecting and evaluating information about the site's location, climate, ecology, history, culture, infrastructure, regulations, and stakeholders. This can help identify the opportunities and constraints for the project, as well as the potential impacts and benefits for the environment and the community. A site analysis can inform the design decisions regarding site selection, site development, water management, energy efficiency, material selection, indoor environmental quality, and innovation12.
References: LEED BD+C Reference Guide, Integrative Process, page 281; Site Analysis for Construction
NEW QUESTION # 65
In a large industrial or commercial building, which energy end uses are classified as systems composed of discrete pieces of equipment that can be metered together for the purposes of Energy and Atmosphere Credit, Advanced Energy Metering?
- A. Water flow system used for public faucets and toilets
- B. Condenser water system with a cooling tower and condenser water pumps
- C. HVAC air system for air conditioning
- D. Electrical lighting system during peak use hours
Answer: B
Explanation:
A condenser water system with a cooling tower and condenser water pumps is classified as a system composed of discrete pieces of equipment that can be metered together for the purposes of Energy and Atmosphere Credit, Advanced Energy Metering. This is because the condenser water system is a single energy end use that serves a specific function and can be isolated from other systems1. HVAC air system, electrical lighting system, and water flow system are not considered as single energy end uses, but rather as multiple energy end uses that serve different functions and cannot be easily isolated2.
References:
*LEED v4 for Building Design and Construction, p. 415
*Advanced Energy Metering, p. 2
NEW QUESTION # 66
......
Start your LEED-AP-BD-C Exam Questions Preparation: https://www.dumpstorrent.com/LEED-AP-BD-C-exam-dumps-torrent.html
Realistic LEED-AP-BD-C Dumps Questions To Gain Brilliant Result: https://drive.google.com/open?id=1ynJ9oFH5M5CHDPgweEgxBY1Z_mWmOTz2