TPCB PTOE Real Exam Questions and Answers FREE [Q103-Q118]

Share

TPCB PTOE Real Exam Questions and Answers FREE

Exam Dumps PTOE Practice Free Latest TPCB Practice Tests

NEW QUESTION # 103
For a signalized intersection with a volume-to-capacity ratio of 0.95 and a cycle length of 80 seconds, what is the average control delay per vehicle per the HCM?

  • A. 55 seconds
  • B. 35 seconds
  • C. 45 seconds
  • D. 65 seconds

Answer: A


NEW QUESTION # 104
For a horizontal curve on a road with a design speed of 65 mph, a superelevation rate of 8%, and a side friction factor of 0.12, what is the minimum radius per AASHTO?

  • A. 1,500 feet
  • B. 1,650 feet
  • C. 1,200 feet
  • D. 1,350 feet

Answer: D


NEW QUESTION # 105
18 crashes occurred on a 3.2-mile section of two-lane road during a 2-year period. The AADT on this road is
13,000 vehicles per day. What is the crash rate?

  • A. 43 crashes per 100 million vehicle miles
  • B. 118 crashes per 100 million vehicle miles
  • C. 136 crashes per 100 million vehicle miles
  • D. 59 crashes per 100 million vehicle miles

Answer: D


NEW QUESTION # 106
Per the AASHTO Roadside Design Guide, a recoverable slope for a roadside is equal to or flatter than:

  • A. 1V:6H
  • B. 1V:3H
  • C. 1V:4H
  • D. 1V:5H

Answer: C


NEW QUESTION # 107
A freeway with three lanes per direction experiences an incident blocking two lanes. According to typical capacity reduction factors, what is the percent capacity reduction?

  • A. 100%
  • B. 65%
  • C. 51%
  • D. 83%

Answer: D


NEW QUESTION # 108
A signalized intersection has a lost time of 4 seconds per phase and 4 phases. If the desired volume-to- capacity ratio is 0.85, what is the minimum cycle length to handle a critical lane volume of 1,200 vehicles
/hour?

  • A. 80 seconds
  • B. 60 seconds
  • C. 100 seconds
  • D. 120 seconds

Answer: C


NEW QUESTION # 109
What does Transportation Systems Management and Operations (TSMO) focus on?

  • A. Limiting access to public transportation
  • B. Increasing vehicle speeds on highways
  • C. Operational improvements to maintain or restore system performance
  • D. Building new transportation infrastructure

Answer: C


NEW QUESTION # 110
An owner requested bids for an office building, and a contractor bid $1.1M. Two months later, the owner asked to reduce the price to $1M. Under contract law, which is the fairest option?

  • A. The contractor must do the work for $1M
  • B. The contractor is entitled to demand the original $1.1M bid
  • C. The original bid has expired since the owner took too long to respond
  • D. The contractor may walk away and refuse to do the job for the reduced sum

Answer: D


NEW QUESTION # 111
A licensee makes a professional judgment which is overruled. The licensee believes that the life, health, property, or welfare of the public is endangered. The licensee should inform:

  • A. His client
  • B. A or B and C
  • C. His employer
  • D. Other authority as may be appropriate

Answer: B


NEW QUESTION # 112
A traffic signal timing plan includes a leading pedestrian interval (LPI) of 3 seconds. What is the primary purpose of the LPI?

  • A. To extend the green phase
  • B. To reduce vehicle delay
  • C. To increase pedestrian visibility and safety
  • D. To synchronize adjacent signals

Answer: C


NEW QUESTION # 113
Five signalized intersections are spaced at 1400 ft intervals along a two-way arterial street. What would be the BEST cycle length for a coordinated signal system if the desired progression speed is 35 mph?

  • A. 85 seconds
  • B. 100 seconds
  • C. 70 seconds
  • D. 110 seconds

Answer: D


NEW QUESTION # 114
Which of the following is NOT considered an ITS strategy?

  • A. Variable speed limits
  • B. Electronic toll collection
  • C. Service patrol vehicles
  • D. GPS locating systems for transit vehicles

Answer: C


NEW QUESTION # 115
What is the primary function of a traffic signal?

  • A. To alternately assign the right-of-way to various traffic movements at an intersection
  • B. To minimize delay and travel time to all users
  • C. To provide protection for pedestrians and other non-motorized users
  • D. To maximize the capacity of an intersection

Answer: A


NEW QUESTION # 116
A client signs a contract for 10 hours of survey work at $20/hour but breaks the contract before work begins.
How much in compensatory damages are paid to the construction company?

  • A. $0
  • B. $100
  • C. None of the above
  • D. $200

Answer: D


NEW QUESTION # 117
A freeway segment with a base capacity of 2,400 passenger cars per hour per lane is adjusted for 10% trucks (PCU = 2.0) and a PHF of 0.90. What is the adjusted capacity per lane?

  • A. 2,080 vehicles/hour
  • B. 2,240 vehicles/hour
  • C. 2,160 vehicles/hour
  • D. 1,920 vehicles/hour

Answer: A


NEW QUESTION # 118
......

Verified PTOE Exam Dumps Q&As - Provide PTOE with Correct Answers: https://www.dumpstorrent.com/PTOE-exam-dumps-torrent.html

PTOE Exam Questions | Real PTOE Practice Dumps: https://drive.google.com/open?id=1DTqyvWwrcjK8B22BjLRYwX7bYr2i1-3j