Valid Way To Pass SAP Certified Associate's  C_ACTIVATE13 Exam


SAP Activate Project Manager Certification Exam Details:

Sample QuestionsSAP Activate Project Manager Certification Sample Questions
Duration180 mins
Passing ScoreC_ACTIVATE13 - 65%
LevelAssociate
Exam NameSAP Certified Associate - SAP Activate Project Manager
Exam CodeC_ACTIVATE13
Schedule ExamSAP Training
Exam Price$550 (USD)
Reference BooksACT100 (SAP S/4HANA 1809)
ACT200 (SEE COURSE DETAIL)
Number of Questions80


SAP C_ACTIVATE13 Exam Description:

The "SAP Certified Associate - SAP Activate Project Manager" certification exam verifies that the candidate has the knowledge required in the area of SAP project management. This certificate builds on basic consultant skills and experience that is then refined by practical experience during several projects. This exam validates whether SAP focused project managers have advanced business skills and the ability to apply methodologies and tools. Aside from advanced communication and presentation skills, this certificate also verifies that the project manager has skills to manage internal and external stakeholders, basic knowledge of change management processes, and communicating these processes to others. This exam validates that project manager can successfully manage the end-to-end transition of the project from Sales to Realization, can develop roadmaps for project execution, and understand testing and quality management. In particular for SAP related projects, the exam verifies that the Project Manager can apply the SAP Activate Methodology.

 

NEW QUESTION 20
Which of the following is not correct about Fit/Gap Analysis?
There are 2 correct answers to this question.
Response:

  • A. Drive towards adopting customers processes.
  • B. Validate pre-activate and pre-assembled solution in the development system.
  • C. Minimize the needs for rework during realization.
  • D. Prioritize delta requirement and gaps.

Answer: A,B

 

NEW QUESTION 21
What is the purpose of the Solution Builder tool in the SAP Activate Guided Configuration?
Please choose the correct answer.
Response:

  • A. To personalize activated, ready-to run business processes
  • B. To create customer-specific scope items
  • C. To create delta building blocks for complementary content
  • D. To activate the Best Practices content

Answer: D

 

NEW QUESTION 22
Which statements are part of the 5 Golden Rules for SAP S/4HANA Cloud, Single Tenant Edition?
There are 2 correct answers to this question.
Response:

  • A. Use SAP Solution Manager 7.2 with Focused Build.
  • B. Stick to the security standards of the customer organization.
  • C. Document deviations from Golden Rules for transparency and future use in upgrades.
  • D. Foster a cloud mindset and adherence to the Fit-to-Standard approach.

Answer: C,D

 

NEW QUESTION 23
According to the Definition of Done, which activity must be completed for each sprint?
Please choose the correct answer.
Response:

  • A. Functionality must be released to the business
  • B. The Solution must be built and configured in the development system (DEV)
  • C. Functionality must be tested in the Quality system (QAS)
  • D. End user training must be delivered

Answer: B

 

NEW QUESTION 24
What is a benefit of using Guided Configuration instead of the Implementation Guide?
Please choose the correct answer.
Response:

  • A. It ensures configuration is done using SAP Solution Manager
  • B. It eliminates the need for Content Lifecycle Management
  • C. It ensures SAP updates do NOT conflict with customer configurations
  • D. It eliminates the need to generate transport requests for configuration settings

Answer: C

 

NEW QUESTION 25
Which activities are part of the Application: Solution Adaption work stream of SAP Activate for new implementations?
There are 3 correct answers to this question.
Response:

  • A. Value Audits
  • B. Scope Validation
  • C. Change Management Plan
  • D. Production Support Plan
  • E. Value Determination

Answer: A,C,E

 

NEW QUESTION 26
What does the Content element of SAP Activate provide?
There are 3 correct answers to this question.
Response:

  • A. Migration Content
  • B. Business Processes Content
  • C. End-User guides
  • D. Functional Specifications for WRICEF development
  • E. Integration Content

Answer: A,B,E

 

NEW QUESTION 27
Which activity helps the Project Team add User Stories to the Product Backlog?
Please choose the correct answer.
Response:

  • A. Conducting the Solution Validation workshop
  • B. Assessing Project Risks
  • C. Preparing a Project Schedule
  • D. Planning the User Acceptance Test

Answer: A

 

NEW QUESTION 28
Which of the following is not correct about the REALIZE phase?
There are 2 correct answers to this question.
Response:

  • A. The beginning of the Realize phase the team prepares a list of all the requirements in a backlog.
  • B. Detailed design workshops are held.
  • C. The project team ensures that the build is meeting the business requirements.
  • D. The team prepares for operations so that the functionality can be brought live.

Answer: A,B

 

NEW QUESTION 29
Which component of SAP Activate offers customers a reference solution in the cloud for a quick start?
Please choose the correct answer.
Response:

  • A. SAP Implementation Assistant
  • B. SAP Best Practices
  • C. Guided Configuration
  • D. SAP Activate Methodology

Answer: B

 

NEW QUESTION 30
What is the purpose of the scrumboard?
Please choose the correct answer.
Response:

  • A. To manage the resource load
  • B. To document the results of integration testing
  • C. To visualize team progress
  • D. To show the functional breakdown of the solution scope

Answer: C

 

NEW QUESTION 31
Which of the following is not a characteristic that the quality principles are based on?
Please choose the correct answer.
Response:

  • A. Experience of Typical Pitfalls
  • B. International standard
  • C. Best Practices
  • D. SAP Quality Award example winners

Answer: B

 

NEW QUESTION 32
Which activities are part of the Design and Configuration application of the SAP Activate methodology?
There are 2 correct answers to this question.
Response:

  • A. Conduct Scope Validation
  • B. Confirm Integration prerequisites
  • C. Schedule kick-off workshop
  • D. Perform Fit/Gap Analysis

Answer: A,D

 

NEW QUESTION 33
What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition?
Please choose the correct answer.
Response:

  • A. SAP Best Practices
  • B. Rapid prototyping
  • C. Full project SCRUM
  • D. Project team training

Answer: A

 

NEW QUESTION 34
In which phase of the SAP Activate methodology does the team complete the Transformation Planning?
Please choose the correct answer.
Response:

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: D

 

NEW QUESTION 35
In which SAP Activate methodology phase does the team complete the Transformation Strategy?
Please choose the correct answer.
Response:

  • A. Prepare
  • B. Explore
  • C. Deploy
  • D. Realize

Answer: A

 

NEW QUESTION 36
Via which media does SAP provide Ready-to-run systems for SAP S/4HANA deployments?
There are 2 correct answers to this question.
Response:

  • A. SAP Cloud Appliance Library
  • B. Blu-ray disks
  • C. SAP Solution Builder tool
  • D. SAP App Center

Answer: A,B

 

NEW QUESTION 37
Which estimation technique can be used in to size the User Stories during Sprint Planning?
Please choose the correct answer.
Response:

  • A. Detailed bottom-up effort estimate that breaks each User Story up into hours or shorter tasks
  • B. Detailed bottom-up effort estimate by the Scrum Master in Story Points based on the User Story complexity
  • C. Relative estimate in Ideal Person Days that reflects the best estimate provided by the project team
  • D. Product Owner's relative estimate of the effort that will be needed to implement the User Story

Answer: D

 

NEW QUESTION 38
Which tools does SAP Activate provide to support Guided Configuration?
There are 3 correct answers to this question.
Response:

  • A. Solution Builder
  • B. Model Company
  • C. Self Service Configuration
  • D. Expert Configuration
  • E. SAP Solution Composer

Answer: A,C,D

 

NEW QUESTION 39
In which of the following project phases is it important to plan and schedule data loads followed by load validation activities?
Please choose the correct answer.
Response:

  • A. Deploy
  • B. Prepare
  • C. Explore
  • D. Realize

Answer: C

 

NEW QUESTION 40
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
Please choose the correct answer.
Response:

  • A. Go-Live scope is fixed on the first of January the following year.
  • B. Project scope and planning are completed and final.
  • C. User Stories are in a Ready state for NO more than the first three Sprints.
  • D. Timelines of the Sprint may differ due to the workload.

Answer: C

 

NEW QUESTION 41
Why is there NO Sandbox system in the "New Implementation of SAP S/4HANA Cloud, Single Tenant Edition" transition path?
Please choose the correct answer.
Response:

  • A. Because the customer may use the SAP Model Company
  • B. Because the Fit-to-Standard workshop is conducted using the Q-system
  • C. Because SAP S/4HANA Cloud, Single Tenant Edition, contains predefined business processes which should NOT be changed
  • D. Because the project team uses the DEV system to confirm solution fit and define delta requirements

Answer: A

 