NEW QUESTION 59
An IT director asks Nexus Integration Team Scrum Master if Nexus Integration Team contains dedicated members who do the integration work.
What should be the response from the Nexus Integration Team Scrum Master? Select two best answers.
- A. Nexus Integration Team is responsible for doing the integration work
- B. As per Nexus Framework, Nexus Integration Team does not do the integration work
- C. Nexus Integration Team does not have dedicated members and it consists of Product Owner, Scrum Master and one/more members from the development teams
- D. The Nexus Integration Team contains the dedicated members
Answer: B,C
NEW QUESTION 60
Scrum Master of one of the team can also act as a Scrum Master in Nexus Integration Team. True or False?
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION 61
During which situations, the stakeholders might get concerned about the progress? (Choose all that apply)
- A. Developers are struggling to answer the questions about the increment
- B. If an integrated increment is not presented during the Nexus Sprint Review
- C. There is an ambiguity about the completeness of a PBI
- D. If the Nexus Sprint Goal is not met consistently
Answer: A,B,C,D
NEW QUESTION 62
Definition of Done is always same for Nexus and all individual Scrum Teams. True or False?
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 63
How many product backlogs should be maintained in a Nexus?
- A. One
- B. One per team
- C. Two per team
- D. Depends on the product
Answer: A
NEW QUESTION 64
What is the recommended number of teams per Nexus?
- A. 3 to 9
- B. 2 to 5
- C. 3 to 12
- D. 4 to 10
Answer: A
NEW QUESTION 65
What is the technical debt?
- A. The money sponsor will lose if the project fails
- B. Technical Debt may represent additional cost a team may incur due to poor design of code
- C. The money spent on the project so far
- D. The money invested on the infrastructure of the project
Answer: B
NEW QUESTION 66
Karen was new to Scrum when the product development started. After 7 Sprints, she gained a lot of experience as a team member and would like to join the Nexus Integration Team. Is she a good candidate to be part of NIT?
- A. No, because NIT membership remains same from Sprint 1 to last Sprint
- B. No, NIT members require several years of experience in Scrum
- C. No, because internal team members cannot be part of NIT
- D. Yes, because Karen is now an experienced team member
Answer: D
NEW QUESTION 67
Nexus with 3 teams have selected 4 PBIs for the upcoming Sprint. Team A will work on Item 1, Team B will work on Item 2 & 3, Team C will work on Item 4. Item 3 has a dependence on Item 2.
Which PBI is the most concerning?
- A. Item 2, because Item 3 has dependence on it
- B. All the 4 PBIs
- C. Item 3, because it cannot proceed without the completion of Item 2
- D. None of the PBIs
Answer: D
NEW QUESTION 68
Who coaches and guides the Scrum Team in the application of Nexus?
- A. Product Owner
- B. Project Manager
- C. Nexus Integration Team
- D. Scrum Integration Team
Answer: C
NEW QUESTION 69
All the development team members need not attend Nexus Daily Scrum. True or False?
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION 70
How does Technical Debt impact the product?
- A. It'll get difficult to add new features
- B. It leads to false assumptions about the state of the product
- C. It'll take longer to solve the existing bugs
- D. It'll get difficult to get additional funding for the product
Answer: A,B,C
NEW QUESTION 71
Who is an appropriate person to represent an individual team in Nexus Daily Scrum?
- A. Product Owner
- B. Customer
- C. A developer working on an item which has cross team dependencies
- D. Scrum Master
Answer: C
NEW QUESTION 72
Adding additional resources to Nexus will result in the value that is being delivered. True or False?
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 73
3 teams are working in a Nexus on development of a mobile application that will support existing customers who were using only the website so far. They are half way through the backlog and their estimation techniques are mostly accurate. Each team's performance has been consistent. During Sprints 5 and 6, all the teams worked only on the backlog items related to the screens in the app. Their velocity was as follows: Team A (20,20), Team B (5,6) and Team C (18,16).
Is there a need to review the skill sets of Team B with respect to screen development and take necessary steps for their improvement?
- A. Yes
- B. No
Answer: A
NEW QUESTION 74
Requirement number 22 is being worked by Team C in a Nexus. Stakeholders are expecting this key feature to be demonstrated in the upcoming Nexus Sprint Review. Just 2 days prior to the review, the team identified a defect in one of the testing scenarios. It has been determined that Team C doesn't have the skillset to resolve the defect in such a short time. Select two BEST possible options the Nexus team can take to resolve the situation.
- A. Postpone the requirement to next Sprint
- B. NIT Scrum Master can look for specialists outside the Nexus who have the skills to resolve the issue
- C. If a resource in other teams in Nexus has the skillset to resolve the issue, they should be brought in to NIT and the whole NIT can work on the issue
- D. Find the resources who have the skills and extend the Sprint to provide sufficient time to resolve the issue
Answer: B,C
NEW QUESTION 75
There can be two product backlogs in a Nexus. True or False?
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 76
Who is a mandatory member of Nexus Integration Team?
- A. Product Owner
- B. Customer
- C. Senior Development Team member
- D. Business Analyst
Answer: A
NEW QUESTION 77
How does technical debt impact product development?
- A. The code written becomes unusable when there is technical debt
- B. Without clearing technical debt, code complexity increases with time
- C. It makes it difficult for the developers to implement new features or fix bugs
- D. Product Owner may not be able to get additional funding if there is technical debt in the project
Answer: B,C
NEW QUESTION 78
During the first 2 Sprints of a product development, Team A's velocity is 10 points whereas Team B's velocity is 20 points.
Which team is performing better?
- A. Team B is performing better
- B. Team's performance cannot be determined by comparing the velocity of another team
- C. Team A is performing better
Answer: B
NEW QUESTION 79
During the Nexus Sprint Retrospective, it was discovered that a team has not been conducting their individual Daily Scrum's over the past few weeks. Who is accountable for ensuring the Nexus framework is understood and enacted?
- A. Developers
- B. Product Owner
- C. Nexus Integration Team
- D. Scrum Master on the Nexus Integration Team
Answer: D
NEW QUESTION 80
5 Scrum teams with 8 members each are working in a Nexus. They are struggling to create a DONE increment every Sprint. The scope is being adjusted often due to newly discovered dependencies and complications.
Which techniques can be use to manage dependencies effectively? Select two best answers
- A. Nexus Integration team should perform additional product backlog refinement
- B. Reorganize the team structure if the dependencies are around skills
- C. Reorder Product backlog items by factoring in the dependency
- D. Merge the teams that often have work with a lot of dependencies
Answer: B,C
NEW QUESTION 81
What is true about Nexus Daily Scrum? Select all that apply.
- A. It helps individual teams to plan their work based on the latest cross-team issues and dependencies
- B. It is held before teams' Daily Scrum
- C. It is an optional event in Nexus
- D. It is to make integration issues transparent
Answer: A,B,D
NEW QUESTION 82
Nexus Daily Scrum replaces the individual team's Daily Scrum. True or False?
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 83
When does the Nexus Sprint Planning end?
- A. When the representatives of each team meet after the individual teams' Sprint planning
- B. When the Product Owner says so
- C. When all the individual teams finish their Sprint Planning
- D. When the expected results of the Nexus Sprint Planning are met
Answer: D
NEW QUESTION 84
......